Mark a chalk on subsequent roof layers upward.
How to shingle a hip roof with architectural shingles.
The middle of the shingles on each new row should line up with two abutting shingles on the previous row.
Carry on with placing complete shingles unless your row completes.
You can cut the layered edge of architectural roof shingles and use the cut flat piece as your starter roof single.
That s how the guys.
To make the shingle flush they would cut a short slice parallel with the ridge.
The second step involves placing the first shingle on your roof.
The hip shingles continued all the way to the ridge and that last shingle was cut to length so as to avoid covering the open ridge rafter.
Bending and overlapping these flaps the guys would put two more nails to anchor it in place.
Apply the first real course of architectural shingles so that the tabs reach the lower edge of the starter course.
The next row of shingles should be placed directly above the first row which makes it two tiles thick.
After both hips were finished the guys would place a shingle along the ridge.
Then finish by placing the last caps at the very top of the roof.
Apply a cover of starter architectural shingles.
When you are placing the shingles on the top row you need to cut it 6 inches from the left corner with the help of utility knife.
Attach each shingle with three nails one in the center and one each on each side.
You need to alternate a full shingle with a half shingle for the starting shingles at the hip ridge as you move up the roof.
In summary to install the ridge cap shingles you simply separate them where they are perforated bend them over the peak and nail them down.
Start from the bottom edge of the ridge and secure each shingle with 1 1 2 inch nails.
How to shingle a hip roof ridge will be done as follows.
After that correctly positionthe first shingle and properly snap a line of chalk across the roof to mark the top layer of the shingles.
The guys would cut a second shingle to overlap the back half of the first one.
If you want to keep your roof from getting potential water damage then you need to start your roofing project by adding flashing to the ridges and by adding strips of tin to the edges of your hip roof.
Trim the very last shingle on each ridge as needed.
Step 10 use roofing cement to glue the last shingle on the hip roof in place where the ridges meet.